Offshore Wind Power Development In Taichung Port

Skip Label and go to Content

Offshore Wind Power Development In Taichung Port

The goal of offshore wind power capacity by 2025 will be 5.5GW.

In Taichung port, the scope of offshore wind power development is:

1.Turbine pre-assembly area:

(1)No.1 pre-assembly area: #5A,#5B heavy wharf and the hinterland of wharf #5A,#5B,#4C(around 12.8ha)

(2)No.2 pre-assembly area: #2 heavy wharf and the hinterland of wharf #2,#4B(around 7ha)

(3)No.3 pre-assembly reserve area: #36 heavy wharf and the hinterland (around 20ha)

 

2.Localized turbine parts manufacturing area:

#106 heavy wharf, the hinterland of wharf #106 and Industrial Zone (II), total area is around 89.4ha.

 

3.GWO training center:

TIPC invited a number of leading offshore wind power enterprises to development a Joint Venture company to set up a GWO training center in Taichung Port. It is estimated to be operated by the beginning of 2019. The existing  TIPC's Training Park(TIPA) is able to provide services of classrooms, meals, and accommodations for GWO participants as well as the technicians for wind farm construction and operation. The training categories including advanced wind power training customized training program, GWO BST & Refresh course.  


 altTrainging Center and Accommodation Building of TIPA


 altExterior and interior of TIPA building

4.O&M base


 altO&M Base

 
 
 
 
 
 


Offshore Wind Power Development in Taichung Port

 

Download the Offshore Wind Power Development in Taichung Port

 




 altOffshore Wind Power Development in Taichung Port

 

Taichung Port offshore wind quay information
Item Description Construction schedule
(estimated)
Wharf #2 ·  250m in length
·  Depth of water: -11m
·  Heavy-bearing-capacity(Quayside):3 ton/m2、10 ton/m2
·  with hinterland of 7ha (include hinterland of #2、#4B)
·  Completed by the end of Y2018


 
Wharf #5A and #5B ·  400m in length
·  Depth of water: -11m
·  Heavy-bearing-capacity(Quayside):50 ton/m2
·  with hinterland of 12.8ha (include hinterland of #5A、#5B、#4C)
·  Wharf #5A: estimated to be completed by the end of Y2019
·  Wharf #5B: estimated to be completed by the Q2 of Y2020


 
Wharf #36 ·  340m in length
·  Depth of water: -12m
·  Heavy-bearing-capacity(Quayside):20~40 ton/m2
·  with hinterland of 15ha
·  estimated to be completed by Q4 Y2020


 
Wharf #106 ·  450m in length
·  Depth of water: -13m
·  Heavy-bearing-capacity(Quayside):10~40 ton/m2
·  with hinterland of 5.4ha
·  Heavy-bearing-capacity 100m part( 40 ton/m2): estimated to be completed by the end of Y2019
·  350m: estimated to be completed by the end of Y2020
Construction of public road and facilities on Industrial Zone (Ⅱ) ·  South-north road: around 1,068m in length, East-west road: around 725m in length
·  Roads are around 30m in width
South-north road: estimated to be completed by  Y2020
   
Last updated:2019-10-03